Owner: State of Idaho Transportation Department
Client Name: State of Idaho Transportation Department
The Sutor Group was engaged by the State of Idaho Transportation Department to assist it in the evaluation of the damage claim submitted by M.A. DeAtley Construction, Inc. DeAtley submitted a claim in the amount of approximately $700,000.
The project consisted of the grading, drainage and plant mix paving of 7.05 miles of US-95 and crushing, screening and stockpiling of anti-skid materials.
DeAtley asserted a delay claim arising from previously approved change orders..
DeAtley submitted an extended field and home office overhead claim. DeAtley asserted that they were delayed for 129 work days.